Colombia terminates the Bucaramanga-Pamplona road contract early
ANI Statement
This is an automated translation of the press release issued in Spanish
The National Infrastructure Agency (ANI) regarding the Bucaramanga-Pamplona project reports that:
1. Given the unviability of the project, the parties agreed to the early termination of Concession Contract No. 002 of 2016, given the impossibility of executing the Works Plan established for the road project.
2. This early termination is carried out taking into account that:
. The environmental license granted by the National Environmental License Agency (ANLA) for the construction of Functional Unit 1 established among the obligations for the development of the project: Submit in the first Environmental Compliance Report - ICA -, the documentary supports where it is evidenced the consultation with the Municipal Authority or other Authorities related to the proposed interventions within the tertiary road infrastructure.
. Despite the numerous efforts carried out by the ANI and the concessionaire with the authorities of the municipality of Floridablanca, it was not possible to agree with the Mayor's Office on the use of the industrial roads required by the project for the execution of the works of Functional Unit 1 or Connecting C1-C2, which constitutes an Event Exempt from Liability, which causes the total suspension of the contractual term.
. This situation was recognized by the Arbitration Court in the Award issued on March 28, 2023 and also reinforced by the Decision of the Panel of Friendly Composers of the Project in a decision of September 4, 2023.
. The impossibility of executing Functional Unit 1 or Connecting Unit C1-C2 generated the loss of validity of the project's Works Plan, affecting the execution of this and the other Functional Units, as well as the possibility of obtaining financing to execute the entire contract. .
3. Due to the situations stated, as recognized by the pronouncements of the Arbitration Award and the decision of the Panel of Friendly Composers, the ANI and the concessionaire show that several of the causes have been established for the early termination of the contract, therefore The reversal stage must begin, which will last 300 calendar days, in which the concessionaire will carry out all the necessary activities to comply with the delivery of the road corridor to Invías.
4. While the reversal stage is underway, the ANI and the concessionaire Autovía Bucaramanga Pamplona SA have agreed to carry out different interventions at critical points of the Bucaramanga-Pamplona corridor, with the aim of guaranteeing the operation and passability of the road, for which They allocated $25,000 million pesos.
5. Likewise, during the execution period of the interventions at critical points and until the reversion of the corridor to the Invías, the concessionaire will continue with the operation and maintenance activities in the road corridor.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Infrastructure (Colombia)

Three groups after US$250mn Colombia airport concession
The 30-year contract should be awarded in the fourth quarter and includes financing, administration, operation and maintenance, among other items.

CAF allocates US$2.74bn for sustainable development of Latin America and the Caribbean
At its meeting in Lima, CAF approved 14 loans for 9 countries, focusing on social inclusion, infrastructure, competitiveness and climate action, an...
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Infrastructure (Colombia)
Get critical information about thousands of Infrastructure projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Western Longitudinal Avenue (ALO), Northern Section
- Current stage:
- Updated:
2 months ago
- Project: New Regional Hospital of Fusagasugá
- Current stage:
- Updated:
2 months ago
- Project: Turbo - Cupica Interoceanic Train (Darién Train, Transoceanic Train)
- Current stage:
- Updated:
2 months ago
- Project: Catatumbo Train
- Current stage:
- Updated:
2 months ago
- Project: Boyacá Transversal Improvement (Puerto Boyacá - Otanche - Chiquinquirá)
- Current stage:
- Updated:
2 months ago
- Project: Valle del Cauca suburban train
- Current stage:
- Updated:
3 months ago
- Project: New cable car Bogotá - La Calera (Cable car Bogotá - San Rafael Ecological Park)
- Current stage:
- Updated:
3 months ago
- Project: Western longitudinal avenue (ALO), south section
- Current stage:
- Updated:
3 months ago
- Project: Andes - Orinoquia railway connection (Puerto Gaitán - Puerto López - Villavicencio)
- Current stage:
- Updated:
3 months ago
- Project: Bucaramanga External Road Ring
- Current stage:
- Updated:
3 months ago
Other companies in: Infrastructure (Colombia)
Get critical information about thousands of Infrastructure companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Empresa Férrea Regional S.A.S.  (EFR Cundinamarca)
-
The description included in this profile was taken directly from an official source and has not been modified or edited by BNamericas’ content team. However, it may have been au...
- Company: PAYC S.A.S.  (PAYC)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: Consorcio Providencia 2016
-
Consorcio Providencia 2016 is a Colombian consortium established in 2015 by local firms Sonacol and MSB Solutions, and Spanish firm Assignia Infraestructuras. In 2015, the conso...
- Company: Consorcio DSC
- Company: Transpetrol LTDA.  (Transpetrol)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: Tipiel S.A.  (Tipiel)
-
Tipiel S.A. is an engineering and construction company controlled by TechnipFMC PLC, a French service company for oil and gas industry. Incorporated in 1975, it carries out stud...
- Company: Alcaldía Municipal de Ibagué
- Company: Intermar Shipping Ltda.  (Intermar Shipping)
-
Intermar Shipping Ltda is based in Colombia with offices in Cartagena, Santa Marta and Barranquilla. The company, with over 20 years of maritime logistics experience, offers int...
- Company: Alcaldía de Pereira
- Company: APP GICA S.A.  (APP Gica)
-
APP Gica S.A. is a Colombian public-private partnership made up of Constructora Colpatria, Mincivil, Termotécnica Coindustrial, Latinco and HB Estructuras Metálicas. It was crea...